Apartment Renovation Contract: Sample, Estimate, Deadlines and Penalty
Documents and deals6 min read
How to draw up an apartment renovation contract in Russia: sample with estimate, stages, advance and warranty, penalty under consumer law, 8 mistakes.

A renovation most often ends in a dispute because the contract lacks two things: an estimate and a date. Without them you can prove neither a delay nor an overrun.

The one-minute calculation
The renovation price under the contract is 640,000 ₽. The deadline was missed by 5 days. The figures are illustrative.
| Line | Calculation | Amount, ₽ |
|---|---|---|
| Penalty for 1 day | 640,000 × 3% | 19,200 |
| For 5 days | 19,200 × 5 | 96,000 |
| Cap | no more than the price of the work | 640,000 |
For a consumer the consumer protection law applies, so the size of the penalty does not need to be written in, but you may refer to the law.
What to write in the contract
| Clause | What to write |
|---|---|
| Parties | Customer's full name and passport data, contractor's details |
| Object | Address, area, rooms |
| Work | A list per the estimate and an appendix with volumes |
| Materials | Who buys, who approves |
| Deadlines | Start, end, schedule by stages |
| Price | Estimate, firm or approximate, procedure for changes |
| Payment | Advance and stages |
| Acceptance | Certificate by stages, remarks |
| Warranty | Period for work and materials |
| Liability | Penalty, compensation of damage |
| Access and order | Keys, cleaning, neighbours |
Apartment renovation contract: sample
WORK CONTRACT No. [number] for apartment renovation [city], [date]
[Customer's full name], passport [series, number], hereinafter the "Customer", and [contractor name], TIN [number], represented by [position, full name], hereinafter the "Contractor", have concluded this contract.
1. Subject. The Contractor renovates the apartment at [address] according to the estimate (Appendix No. 1), and the Customer accepts the work and pays for it.
2. Deadlines. Work starts on [date]. It ends on [date]. The stages are defined by the schedule (Appendix No. 2).
3. Price and payment. The price of the work is [amount] ₽, [including / excluding] VAT. An advance of [amount] ₽ is paid before work starts. The rest is paid by stages after the certificates are signed.
4. Materials. Materials are bought by [the Contractor / the Customer] from an agreed list. Replacing materials is allowed only with the Customer's consent.
5. Additional work. Anything not in the estimate is done only after written agreement of price and deadline.
6. Acceptance. Work is accepted by stages by certificates. Remarks are recorded in the certificate, the period for correction is [number] days.
7. Warranty. The warranty on work is valid for [number] months from the date of the final certificate.
8. Liability. If the Contractor misses the deadline, they pay a penalty in the amount set by the consumer protection law. The Customer ensures access to the premises.
9. Termination. The Customer may terminate the contract at any time, paying for what is already done and reimbursing the Contractor's expenses (Article 32 of the consumer protection law).
10. Signatures and details.
What is in the estimate and why it is the main thing
An estimate is a list of work with units, volumes and prices. If the price is approximate and the contractor realises it will grow, they must warn the customer at once; without that, they will have to perform the work at the previous price (Article 709 of the Civil Code). Ask for an estimate as a table where work and materials are listed separately, and attach it to the contract.
Deadlines and penalty
Under the consumer protection law, for delay in starting or finishing work you can demand 3% of the price per day, but the total cannot exceed the price of the work (Article 28). If the deadline was missed because of your actions, for example you did not open the apartment, the contractor may refer to this. Keep correspondence and certificates of unavailability.
Acceptance and warranty
Accept the work by stages: hidden work (electrics, waterproofing, screed) is accepted before it is covered. Defects are written in the certificate, and during the warranty period you may demand that defects be fixed (Article 723). Be sure to keep receipts and certificates: they will be useful if you have to go to court.
Eight mistakes
No estimate. The cost grows and there is nothing to prove it with.
No end date. A deadline "when ready" does not work.
The whole payment up front. The contractor vanishes with the advance.
No stages. It is impossible to tell what has been accepted.
Materials without a list. They are swapped for cheap analogues.
Extra work orally. Later it turns out it was a paid order.
Acceptance without inspecting hidden work. The screed was covered, and the error stayed inside.
No warranty. Half a year later there is a crack, and nobody to answer for it.
How it works in Mestra
You or a lawyer prepare the contract text and estimate: Mestra has no document templates. But renovation crews and craftsmen get order in their work.
Each site is run as a deal with stages: measurement, estimate, prepayment, rough work, finishing, acceptance. Tasks are assigned to employees with deadlines, photos and certificates are attached in the "Files" tab, and reminders about payments and deadlines arrive automatically. Material balances and purchases are visible in warehouse accounting, and clients' payment debts in a separate tab. We wrote more in Advance and prepayment.
Questions and answers
Is a written form needed?
For an apartment renovation, yes, especially if there is a consumer who is an individual and a substantial sum. A written contract protects both sides.
How to formalise a private craftsman?
A work contract with an individual, preferably a self-employed one. Details in Contract with a self-employed person.
What advance is reasonable?
The law does not fix an amount. Practice: an advance for materials and a small part of the work, the rest by stages.
What if the contractor delayed the work?
Demand in writing that it be finished within a reasonable time, and then use the penalty or withdraw from the contract.
Who answers for hidden defects?
The contractor, while the warranty is valid, but not for damage from use.
Is a hidden-work certificate needed?
Yes, it confirms that you accepted the work before it was covered.
Summary
An apartment renovation contract rests on the estimate, dates, payment stages and the warranty. Mestra runs a site by stages and keeps documents, payments and photos together. The first 15 days are free, no card required.